| Lend Lease BUILDING RAPPORT already commenced so we had to work hard with the design team to integrate the works and mitigate any delays on site.” “Due to the fitout sequencing changing, a whole other series of complications for logistics and construction were introduced.Construction commenced from the basement up to the roof, then jumped up to three and four, then back down to two. This affected our ability to close up the façade and complete compartments on each floor which significantly impacted the final commissioning and balancing for the complex pressurisation regime of the building.” “For me personally, this has been the most challenging project I’ve worked on, but also the most rewarding,” he adds. “Adelaide is a small town in the grand scheme of things, and businesses rely heavily on relationships,” Gary says. “Fortunately, we’ve formed longstanding relationships with our consultants and subcontractors, and we’ve worked together on many difficult and challenging projects.”